15 Years: History of Masai Mara Management Plan Development

The development of the Masai Mara management plan was a complex and prolonged process, reflecting the multifaceted challenges and the need for comprehensive stakeholder involvement. Here’s a detailed expert analysis of the timeline, highlighting key factors and insights:

Initial Approval and Early Development (2007-2012)

  • 2007 Approval: The plan’s development was first approved in 2007 by the former County Councils of Narok and Trans Mara, along with the Mara Conservancy. This initial phase set the groundwork for a structured approach to managing the Masai Mara National Reserve (MMNR).
  • 2008-2012 Planning Phase: Over these five years, the initial planning process unfolded. This period involved significant collaboration and financial contributions from the county councils, the Mara Conservancy, and the African Wildlife Foundation (AWF). The Conservation Development Centre (CDC) played a crucial role in facilitating and drafting the management plan, leveraging its experience from similar projects like the Serengeti National Park and Kenya’s Protected Area Planning Framework (PAPF).

Interruptions and Challenges (2013-2020)

  • 2013 County Council Dissolution: The dissolution of the county councils in 2013 was a significant administrative change that halted the finalization of the plan. This interruption lasted until Narok County, the successor administrative body, took over the responsibility for the plan’s development.
  • 2015-2016 Update and Refinement: An intensive effort to update and refine the draft management plan took place during this period. However, progress was again disrupted by the 2017 general elections, reflecting how political events can impact long-term conservation planning.
  • 2020 COVID-19 Impact: The COVID-19 pandemic prompted renewed efforts to finalize the plan in August 2020. The pandemic’s severe impact on tourism highlighted the need for a robust management strategy to ensure the Reserve’s economic and ecological sustainability. Despite the urgency, this phase also saw delays due to the 2022 general elections.

Finalization and Approval (2021-2023)

  • Early 2023 Approval: The new Narok County administration resumed the process in early 2023. The final review and approval by the Narok County Assembly, followed by the signing into law by the Narok County Governor on February 21, 2023, marked the culmination of over 15 years of planning and development efforts.

Key Insights

Prolonged Timeline

  • 15+ Years: The entire process took more than 15 years from initial approval to final implementation. This extended timeline underscores the complexities involved in developing a comprehensive management plan for a globally significant conservation area like the Masai Mara.

Administrative and Political Challenges

  • Administrative Changes: The dissolution of the original county councils and the transition to Narok County’s administration caused significant delays. Effective management of such transitions is crucial for maintaining momentum in long-term projects.
  • Political Influences: General elections in 2017 and 2022 further delayed the process. Political stability and continuity are vital for the timely completion of conservation initiatives.

Stakeholder Collaboration

  • Multiple Stakeholders: The involvement of various stakeholders, including local councils, the Mara Conservancy, AWF, and CDC, was essential for pooling resources and expertise. However, coordinating such diverse interests added to the complexity and duration of the planning process.
  • Community Involvement: Engaging local communities and stakeholders in the planning process is critical for the plan’s acceptance and successful implementation.

Impact of External Events

COVID-19 Pandemic: The pandemic highlighted vulnerabilities in the Reserve’s economic model, primarily dependent on tourism. This crisis provided an impetus to finalize the management plan to address these vulnerabilities and ensure sustainable management practices.

Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top